The second of the eight pillars of TPM is autonomous maintenance. One of the parts of the autonomous maintenance is OEE for Operators: Overall Equipment Effectiveness. It follows a structured approach to increase the skill levels of personnel whivh people will understand. They will also manage and improve their equipment and processes. Identifying Waste on the Shopfloor is a good guide book. The goal is to change operators from being reactive to working in a more proactive way and the Cmti handbook will help you a lot. To achieve optimal conditions that eliminate minor equipment you have to work hard a lot. It shall in turn stop and reduce breakdowns and defects.
More on Overall Equipment Effectiveness.
According to availability, performance and quality the concept of OEE or Overall Equipment Effectiveness breaks the performance of a manufacturing unit into three distinct and measurable components. All the components, individually or not, points to an aspect of the process. It can be targeted for improvement or just casually. The principle of OEE may also be applicable to any individual work center. It may also be rolled up to department or levels of a plant. This is a tool that also allows drilling down extremely specific analysis. They can be part number, shift or any of several other parameters. It is quiet unlikely that any manufacturing process can run at complete OEE. Hence, many manufacturers are benchmarking their industry. It is to set a challenging target where the 85% is not really uncommon.
The process rate of the Overall Equipment Effectiveness.
The performance portion of the OEE Metric is also known as the process rate. It is a series of calculation which represents the speed at which the work center runs. The center usually runs as a percentage of its designated speed. Additionally, the performance metric is a pure measurement of speed. The speed that is designed to differentiate among the effects of quality and availability is mentioned here. Losses incurred due to wasted performance, often called speed losses, are often not determined. A common approach is to assign the unknown losses as speeded ones.
No comments:
Post a Comment